Summary on the PV projects completed / Podsumowanie ukończonych projektów fotowoltaicznych
31-01-2012
The Management Board of Photon Energy a.s. publishes the following report on PV projects completed between 1 October 2011 till date.
Germany
The following photovoltaic power plants were completed or/and under construction in the reporting period:
- PV power plant in Ellrich with the total installed capacity of 600 kWp; the power plant is eligible for the feed-in-tariff of EUR 22.07/MWh and the installation is expected to be connected to the grid in April 2012
- 400 kWp ground-mounted PV power plant in Ellrich was completed but the applicable tariff is to be confirmed yet; the installation is expected to be connected to the grid in April 2012
- PV rooftop installation in Altentreptow with the total installed capacity of 156 kWp; the power plant is eligible for the feed-in-tariff of EUR 27.08 (weighted average of eligible tariffs within respective capacity ranges). The installation is expected to be connected to the grid in February 2012
- PV rooftop installation on premises of Grundschule Ueckermuende with the total installed capacity of 45 kWp; the power plant is eligible for the feed-in-tariff of EUR 28.27/MWh (weighted average of eligible tariffs within respective capacity ranges); the installation is expected to be connected to the grid in February 2012
- Two PV rooftop installations on premises of Gymnasium Ueckermuende with the total installed capacity of 27 kWp; both power plants are eligible for the feed-in-tariff of EUR 28.74 / MWh; the installation has already been connected to the grid.
- PV rooftop installation on premises of Kindergarten Ueckermuende of the total installed capacity of 25 kWp; the power plant is eligible for the feed-in-tariff of EUR 28.74 / MWh; the installation has already been connected to the grid.
- PV rooftop installation in Demmin with the total installed capacity of 40.5 kWp; the power plant is eligible for the feed-in-tariff of EUR 28.38/MWh (weighted average of eligible tariffs within respective capacity ranges); the installation is expected to be connected to the grid in February 2012.
The project which has not been completed in the reporting period is the 600 kWp ground-mounted PV installation in Herzberg. The feasibility studies of the project revealed that a double grid connection is required which significantly changes the economics and the technical set up of the project. The project is still under revision and the decision on its development will be taken in the course of the upcoming months.
Italy
The following photovoltaic power plants were completed and/or under construction in the reporting period:
- the 261 kWp PV rooftop installation in Verderio was completed and connected to the grid in November qualifying for the feed in premium of EUR 0.265/kWh on top of the electricity sales revenues of more than EUR 0.07/kWh.
- the 998 kWp PV asbestos rooftop in Verrone, Biella province has been under construction and is expected to be connected to the grid before 30 June 2012.
The remaining two projects including: the 900 kWp PV asbestos rooftop Sirone in Lecco province and the 500 kWp PV asbestos rooftop in Fisciano, Salerno province were delayed due to the financing constraints existing on the Italian market (too high costs of debt financing). A separate report on the Italian projects will follow in the course of next weeks.
Australia
The following photovoltaic power plant was under construction in the reporting period:
- 144 kWp PV project in Symostons, including rooftop and ground-mounted installation; the engineering phase has been completed and the project is now in the process of applying for the building permit which is expected to be issued in Q1 2012; the construction of the project is expected to finish in the course of Q1-Q2 2012.
The public tender for Cloncurry Solar Farm has been resolved. Photon Energy has not been successful in winning this tender.
In the course of year 2011 the proprietary portfolio of Photon Energy Group increased by 8.4 MWp (pro-rata 6.9 MWp) and reached 27.05 MWp (pro-rata 25.01 MWp), as of the end of 2011.
Legal basis: § 3 ust. 2 point no.2 of the Appendix 3 to Regulations of the Alternative Trading System - "Current and Periodical Information in the Alternative Trading System". --------------------------------------------------------------------------------------------------------------------------
Zarząd Photon Energy a.s. informuje o ukończeniu następujących projektów fotowoltaicznych w okresie od 1 października 2011 r. do dnia publikacji niniejszego raportu.
Niemcy:
W okresie raportowania ukończone zostały następujące projekty fotowoltaiczne:
- Elektrownia fotowoltaiczna w miejscowości Ellrich o całkowitej, zainstalowanej mocy 600 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 22.07/MWh; planowany termin podłączenia instalacji do sieci to kwiecień 2012 r.
- Elektrownia fotowoltaiczna w miejscowości Ellrich o całkowitej zainstalowanej mocy 400 kWp; poziom taryf gwarantowanych (FiT) nie został jeszcze zatwierdzony; planowany termin podłączenia instalacji do sieci to kwiecień 2012 r.
- Elektrownia fotowoltaiczna w Altentreptow o całkowitej zainstalowanej mocy 156 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 27.08/MWh (średnia ważona z taryf gwarantowanych w odpowiednich przedziałach mocy); planowany termin podłączenia instalacji do sieci to luty 2012 r.
- Elektrownia fotowoltaiczna na budynku Grundschule w miejscowości Ueckermuende o całkowitej zainstalowanej mocy 45 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości 28.27/MWh (średnia ważona z taryf gwarantowanych w odpowiednich przedziałach mocy); planowany termin podłączenia instalacji do sieci to luty 2012 r.
- Dwie elektrownie fotowoltaiczne na budynkach Gymnasium Ueckermuende o całkowitej zainstalowanej mocy 27 kWp; elektrownie objęte są taryfą gwarantowaną (FiT) w wysokości EUR 28.74 /MWh; instalacja jest już podłączona do sieci.
- Elektrownia fotowoltaiczna na budynkach Kindergarten Ueckermuende o całkowitej zainstalowanej mocy 25 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 28.74 /MWh; instalacja jest już podłączona do sieci.
- Elektrownia fotowoltaiczna w miejscowości Demmin o całkowitej zainstalowanej mocy 40.5 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 28.38/MWh (średnia ważona z taryf gwarantowanych w odpowiednich przedziałach mocy); oczekiwany termin podłączenia instalacji do sieci to luty 2012 r.
Projekt, który nie został ukończony w okresie raportowania, to instalacja naziemna w miejscowości Herzberg o całkowitej mocy 600kWp. Studium wykonalności projektu wykazało, iż konieczne jest podłączenie projektu do sieci w dwóch punktach co znacząco zmieniło założenia ekonomiczne oraz techniczne tego projektu. Projekt jest jeszcze w toku analiz a ostateczna decyzja odnośnie jego realizacji zostanie podjęta w ciągu najbliższych miesięcy.
WÅ‚ochy
W okresie raportowania ukończono oraz/lub prowadzono budowę następujących projektów:
- Instalacja fotowoltaiczna o mocy 261 kWp w miejscowości Verderio została ukończona i podłączona do sieci w listopadzie 2011 r. kwalifikując się do taryfy premiowej w wysokości EUR 0.265/kWh powyżej przychodów ze sprzedaży energii elektrycznej, które wynoszą EUR 0.07/kWh.
- Instalacja fotowoltaiczna o mocy 998 kWp w miejscowości Verrone, prowincja Biella jest w toku budowy a jej ukończenie oraz podłączenie do sieci planowane jest do 30 czerwca 2012 r.
Pozostałe dwa projekty tj: instalacja dachowa PV o mocy 900 kWp w miejscowości Sirone, prowincja Lecco oraz instalacja dachowa PV o mocy 500 kWp w miejscowości Fisciano, prowincja Salerno zostały opóźnione ze względu na trudności w finansowaniu projektów na rynku włoskim (zbyt wysokie koszty długu). Odrębny raport na temat projektów włoskich zostanie opublikowany w przeciągu najbliższych tygodni.
Australia
W okresie raportowania ukończono oraz/lub prowadzono budowę następujących projektów:
- Projekt fotowoltaiczny o mocy 144 kWp w miejscowości Symostons, obejmujący instalację dachową i naziemną; faza prac inżynieryjnych została ukończona a projekt oczekuje obecnie na pozwolenie na budowę, które powinno zostać wydane w I kwartale 2012 r.; budowa elektrowni planowana jest na przełomie I / II kwartału br.
Przetarg publiczny na budowę farmy słonecznej Cloncurry Solar Farm został rozstrzygnięty. Spółce nie udało się pozyskać tego kontraktu.
W roku 2011 portfel elektrowni własnych Photon Energy wzrósł o 8.4 MWp (pro-rata 6.9 MWp) i wynosił na koniec roku 27.05 MWp (pro-rata 25.01 MWp).
Podstawa prawna: § 3 ust. 2 Załącznika Nr 3 do Regulaminu Alternatywnego Systemu Obrotu - "Informacje bieżące i okresowe przekazywane w alternatywnym systemie obrotu na rynku NewConnect".
Germany
The following photovoltaic power plants were completed or/and under construction in the reporting period:
- PV power plant in Ellrich with the total installed capacity of 600 kWp; the power plant is eligible for the feed-in-tariff of EUR 22.07/MWh and the installation is expected to be connected to the grid in April 2012
- 400 kWp ground-mounted PV power plant in Ellrich was completed but the applicable tariff is to be confirmed yet; the installation is expected to be connected to the grid in April 2012
- PV rooftop installation in Altentreptow with the total installed capacity of 156 kWp; the power plant is eligible for the feed-in-tariff of EUR 27.08 (weighted average of eligible tariffs within respective capacity ranges). The installation is expected to be connected to the grid in February 2012
- PV rooftop installation on premises of Grundschule Ueckermuende with the total installed capacity of 45 kWp; the power plant is eligible for the feed-in-tariff of EUR 28.27/MWh (weighted average of eligible tariffs within respective capacity ranges); the installation is expected to be connected to the grid in February 2012
- Two PV rooftop installations on premises of Gymnasium Ueckermuende with the total installed capacity of 27 kWp; both power plants are eligible for the feed-in-tariff of EUR 28.74 / MWh; the installation has already been connected to the grid.
- PV rooftop installation on premises of Kindergarten Ueckermuende of the total installed capacity of 25 kWp; the power plant is eligible for the feed-in-tariff of EUR 28.74 / MWh; the installation has already been connected to the grid.
- PV rooftop installation in Demmin with the total installed capacity of 40.5 kWp; the power plant is eligible for the feed-in-tariff of EUR 28.38/MWh (weighted average of eligible tariffs within respective capacity ranges); the installation is expected to be connected to the grid in February 2012.
The project which has not been completed in the reporting period is the 600 kWp ground-mounted PV installation in Herzberg. The feasibility studies of the project revealed that a double grid connection is required which significantly changes the economics and the technical set up of the project. The project is still under revision and the decision on its development will be taken in the course of the upcoming months.
Italy
The following photovoltaic power plants were completed and/or under construction in the reporting period:
- the 261 kWp PV rooftop installation in Verderio was completed and connected to the grid in November qualifying for the feed in premium of EUR 0.265/kWh on top of the electricity sales revenues of more than EUR 0.07/kWh.
- the 998 kWp PV asbestos rooftop in Verrone, Biella province has been under construction and is expected to be connected to the grid before 30 June 2012.
The remaining two projects including: the 900 kWp PV asbestos rooftop Sirone in Lecco province and the 500 kWp PV asbestos rooftop in Fisciano, Salerno province were delayed due to the financing constraints existing on the Italian market (too high costs of debt financing). A separate report on the Italian projects will follow in the course of next weeks.
Australia
The following photovoltaic power plant was under construction in the reporting period:
- 144 kWp PV project in Symostons, including rooftop and ground-mounted installation; the engineering phase has been completed and the project is now in the process of applying for the building permit which is expected to be issued in Q1 2012; the construction of the project is expected to finish in the course of Q1-Q2 2012.
The public tender for Cloncurry Solar Farm has been resolved. Photon Energy has not been successful in winning this tender.
In the course of year 2011 the proprietary portfolio of Photon Energy Group increased by 8.4 MWp (pro-rata 6.9 MWp) and reached 27.05 MWp (pro-rata 25.01 MWp), as of the end of 2011.
Legal basis: § 3 ust. 2 point no.2 of the Appendix 3 to Regulations of the Alternative Trading System - "Current and Periodical Information in the Alternative Trading System". --------------------------------------------------------------------------------------------------------------------------
Zarząd Photon Energy a.s. informuje o ukończeniu następujących projektów fotowoltaicznych w okresie od 1 października 2011 r. do dnia publikacji niniejszego raportu.
Niemcy:
W okresie raportowania ukończone zostały następujące projekty fotowoltaiczne:
- Elektrownia fotowoltaiczna w miejscowości Ellrich o całkowitej, zainstalowanej mocy 600 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 22.07/MWh; planowany termin podłączenia instalacji do sieci to kwiecień 2012 r.
- Elektrownia fotowoltaiczna w miejscowości Ellrich o całkowitej zainstalowanej mocy 400 kWp; poziom taryf gwarantowanych (FiT) nie został jeszcze zatwierdzony; planowany termin podłączenia instalacji do sieci to kwiecień 2012 r.
- Elektrownia fotowoltaiczna w Altentreptow o całkowitej zainstalowanej mocy 156 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 27.08/MWh (średnia ważona z taryf gwarantowanych w odpowiednich przedziałach mocy); planowany termin podłączenia instalacji do sieci to luty 2012 r.
- Elektrownia fotowoltaiczna na budynku Grundschule w miejscowości Ueckermuende o całkowitej zainstalowanej mocy 45 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości 28.27/MWh (średnia ważona z taryf gwarantowanych w odpowiednich przedziałach mocy); planowany termin podłączenia instalacji do sieci to luty 2012 r.
- Dwie elektrownie fotowoltaiczne na budynkach Gymnasium Ueckermuende o całkowitej zainstalowanej mocy 27 kWp; elektrownie objęte są taryfą gwarantowaną (FiT) w wysokości EUR 28.74 /MWh; instalacja jest już podłączona do sieci.
- Elektrownia fotowoltaiczna na budynkach Kindergarten Ueckermuende o całkowitej zainstalowanej mocy 25 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 28.74 /MWh; instalacja jest już podłączona do sieci.
- Elektrownia fotowoltaiczna w miejscowości Demmin o całkowitej zainstalowanej mocy 40.5 kWp; elektrownia objęta jest taryfą gwarantowaną (FiT) w wysokości EUR 28.38/MWh (średnia ważona z taryf gwarantowanych w odpowiednich przedziałach mocy); oczekiwany termin podłączenia instalacji do sieci to luty 2012 r.
Projekt, który nie został ukończony w okresie raportowania, to instalacja naziemna w miejscowości Herzberg o całkowitej mocy 600kWp. Studium wykonalności projektu wykazało, iż konieczne jest podłączenie projektu do sieci w dwóch punktach co znacząco zmieniło założenia ekonomiczne oraz techniczne tego projektu. Projekt jest jeszcze w toku analiz a ostateczna decyzja odnośnie jego realizacji zostanie podjęta w ciągu najbliższych miesięcy.
WÅ‚ochy
W okresie raportowania ukończono oraz/lub prowadzono budowę następujących projektów:
- Instalacja fotowoltaiczna o mocy 261 kWp w miejscowości Verderio została ukończona i podłączona do sieci w listopadzie 2011 r. kwalifikując się do taryfy premiowej w wysokości EUR 0.265/kWh powyżej przychodów ze sprzedaży energii elektrycznej, które wynoszą EUR 0.07/kWh.
- Instalacja fotowoltaiczna o mocy 998 kWp w miejscowości Verrone, prowincja Biella jest w toku budowy a jej ukończenie oraz podłączenie do sieci planowane jest do 30 czerwca 2012 r.
Pozostałe dwa projekty tj: instalacja dachowa PV o mocy 900 kWp w miejscowości Sirone, prowincja Lecco oraz instalacja dachowa PV o mocy 500 kWp w miejscowości Fisciano, prowincja Salerno zostały opóźnione ze względu na trudności w finansowaniu projektów na rynku włoskim (zbyt wysokie koszty długu). Odrębny raport na temat projektów włoskich zostanie opublikowany w przeciągu najbliższych tygodni.
Australia
W okresie raportowania ukończono oraz/lub prowadzono budowę następujących projektów:
- Projekt fotowoltaiczny o mocy 144 kWp w miejscowości Symostons, obejmujący instalację dachową i naziemną; faza prac inżynieryjnych została ukończona a projekt oczekuje obecnie na pozwolenie na budowę, które powinno zostać wydane w I kwartale 2012 r.; budowa elektrowni planowana jest na przełomie I / II kwartału br.
Przetarg publiczny na budowę farmy słonecznej Cloncurry Solar Farm został rozstrzygnięty. Spółce nie udało się pozyskać tego kontraktu.
W roku 2011 portfel elektrowni własnych Photon Energy wzrósł o 8.4 MWp (pro-rata 6.9 MWp) i wynosił na koniec roku 27.05 MWp (pro-rata 25.01 MWp).
Podstawa prawna: § 3 ust. 2 Załącznika Nr 3 do Regulaminu Alternatywnego Systemu Obrotu - "Informacje bieżące i okresowe przekazywane w alternatywnym systemie obrotu na rynku NewConnect".